Moore Park Beach Master Plan - Recap

jjbartels

It is remiss of me to think that everyone knows what the MPB Master Plan is when I talk about it. I am forgetting that a large section of our community was not in the area when the Master Plan consultation and development process started in 2020. I apologise for this oversite and will give a brief outline of what the MPB Master Plan is:


In October 2019, I presented my case to Council for the development of a Master Plan for MPB, which was unanimously supported. I presented my vision and gave the good news to the community at the MPB Community meeting on the 10th December 2019, which was as follows:


𝘍𝘰𝘳 𝘢𝘭𝘭 𝘰𝘧 𝘵𝘩𝘪𝘴 𝘵𝘦𝘳𝘮, 𝘢𝘴 𝘳𝘦𝘲𝘶𝘦𝘴𝘵𝘦𝘥 𝘣𝘺 𝘵𝘩𝘦 𝘊𝘰𝘮𝘮𝘶𝘯𝘪𝘵𝘺, 𝘐 𝘩𝘢𝘷𝘦 𝘣𝘦𝘦𝘯 𝘱𝘶𝘴𝘩𝘪𝘯𝘨 𝘧𝘰𝘳 𝘢 𝘔𝘢𝘴𝘵𝘦𝘳 𝘗𝘭𝘢𝘯 𝘵𝘰 𝘣𝘦 𝘤𝘳𝘦𝘢𝘵𝘦𝘥 𝘧𝘰𝘳 𝘵𝘩𝘦 𝘦𝘯𝘵𝘪𝘳𝘦 𝘤𝘦𝘯𝘵𝘳𝘢𝘭 𝘢𝘳𝘦𝘢 𝘰𝘧 𝘔𝘗𝘉 𝘢𝘯𝘥 𝘯𝘰𝘸 𝘩𝘢𝘷𝘦 𝘵𝘩𝘦 𝘴𝘶𝘱𝘱𝘰𝘳𝘵 𝘳𝘦𝘲𝘶𝘪𝘳𝘦𝘥 𝘵𝘰 𝘦𝘯𝘴𝘶𝘳𝘦 𝘵𝘩𝘢𝘵 𝘵𝘩𝘪𝘴 𝘪𝘴 𝘤𝘰𝘮𝘮𝘦𝘯𝘤𝘦𝘥 𝘪𝘯 𝘦𝘢𝘳𝘭𝘺 2020.

𝘛𝘩𝘦 𝘔𝘢𝘴𝘵𝘦𝘳 𝘗𝘭𝘢𝘯 𝘸𝘪𝘭𝘭 𝘵𝘢𝘬𝘦 𝘪𝘯 𝘵𝘩𝘦 𝘧𝘰𝘳𝘦𝘴𝘩𝘰𝘳𝘦 𝘢𝘳𝘦𝘢𝘴 𝘧𝘳𝘰𝘮 𝘓𝘢𝘴𝘴𝘪𝘨 𝘚𝘵 𝘵𝘰 𝘊𝘭𝘢𝘶𝘥𝘦 𝘋𝘰𝘰𝘭𝘦𝘺 𝘗𝘢𝘳𝘬 𝘢𝘯𝘥 𝘢𝘭𝘴𝘰 𝘪𝘯𝘤𝘭𝘶𝘥𝘦 𝘵𝘩𝘦 𝘤𝘦𝘯𝘵𝘳𝘢𝘭 𝘢𝘳𝘦𝘢 𝘢𝘳𝘰𝘶𝘯𝘥 𝘵𝘩𝘦 𝘩𝘢𝘭𝘭 𝘢𝘯𝘥 𝘰𝘷𝘢𝘭. 𝘛𝘩𝘦𝘳𝘦 𝘸𝘪𝘭𝘭 𝘣𝘦 𝘮𝘶𝘤𝘩 𝘤𝘰𝘮𝘮𝘶𝘯𝘪𝘵𝘺 𝘤𝘰𝘯𝘴𝘶𝘭𝘵𝘢𝘵𝘪𝘰𝘯 𝘪𝘯𝘷𝘰𝘭𝘷𝘦𝘥 𝘸𝘪𝘵𝘩 𝘥𝘦𝘷𝘦𝘭𝘰𝘱𝘪𝘯𝘨 𝘵𝘩𝘦 𝘗𝘭𝘢𝘯 𝘢𝘯𝘥 𝘸𝘦 𝘯𝘦𝘦𝘥 𝘦𝘷𝘦𝘳𝘺𝘰𝘯𝘦 𝘵𝘰 𝘤𝘰𝘯𝘵𝘳𝘪𝘣𝘶𝘵𝘦 𝘵𝘩𝘦𝘪𝘳 𝘪𝘥𝘦𝘢𝘴, 𝘷𝘪𝘴𝘪𝘰𝘯 𝘢𝘯𝘥 𝘷𝘪𝘦𝘸𝘴 𝘴𝘰 𝘵𝘩𝘢𝘵 𝘵𝘩𝘦 𝘧𝘪𝘯𝘢𝘭 𝘳𝘦𝘴𝘶𝘭𝘵 𝘪𝘴 𝘵𝘩𝘦 𝘤𝘳𝘦𝘢𝘵𝘪𝘰𝘯 𝘰𝘧 𝘢𝘯 𝘢𝘳𝘦𝘢 𝘵𝘩𝘢𝘵 𝘔𝘰𝘰𝘳𝘦 𝘗𝘢𝘳𝘬 𝘉𝘦𝘢𝘤𝘩 𝘤𝘢𝘯 𝘣𝘦 𝘱𝘳𝘰𝘶𝘥 𝘰𝘧 𝘢𝘯𝘥 𝘢𝘭𝘴𝘰 𝘣𝘦 𝘢 𝘥𝘳𝘢𝘸 𝘤𝘢𝘳𝘥 𝘧𝘰𝘳 𝘵𝘩𝘦 𝘳𝘦𝘨𝘪𝘰𝘯.

𝘛𝘩𝘦 𝘴𝘵𝘦𝘱𝘴 𝘪𝘯𝘷𝘰𝘭𝘷𝘦𝘥 𝘸𝘪𝘭𝘭 𝘣𝘦-

𝘋𝘦𝘷𝘦𝘭𝘰𝘱 𝘔𝘢𝘴𝘵𝘦𝘳 𝘗𝘭𝘢𝘯 > 𝘚𝘰𝘶𝘳𝘤𝘦 𝘍𝘶𝘯𝘥𝘪𝘯𝘨 > 𝘊𝘳𝘦𝘢𝘵𝘦 𝘢𝘯 𝘰𝘶𝘵𝘴𝘵𝘢𝘯𝘥𝘪𝘯𝘨 𝘢𝘳𝘦𝘢 𝘧𝘰𝘳 𝘵𝘩𝘦 𝘔𝘗𝘉 𝘊𝘰𝘮𝘮𝘶𝘯𝘪𝘵𝘺.



Below is a detailed timeline of what has occurred to date.


Where we are currently at with the Master Plan:


𝗦𝘁𝗮𝗴𝗲 𝟭 𝗨𝗽𝗱𝗮𝘁𝗲:

Tenders have been received and a contract has been signed for the development of Stage 1 of the Moore Park Beach Master Plan being the Community Hub/Community Centre Annex, which will be home to MPB Arts, MPB Men’s Shed, MPB Scouts and many other community groups that need a space to operate from. It will also have the Hub Shop as part of the complex. Local builders, Hallstone Constructions, have been awarded the tender for construction of the Moore Park Beach Community Hub.


Construction drawings are currently being developed based on the concept plans as the tender was for design and construct based on the concept drawings.

The pre-start meeting between BRC, and the contractor was held at the end of January 24, and Hallstone have submitted a construction timeline/program for Stage 1.

Key dates are as follows:

• 80% detailed design hold point and workshop 15/03/24

• Building approvals 29/03/24

• 100% detailed design, certified IFC drawings 01/04/24

• Construction commencement 08/04/24

• Practical completion 23/09/24


Note there is some float built into this program so we will take advantage of any opportunities to make up time.


As soon as Council has a copy of the draft plans, we will meet with the Men’s Shed and all the other community groups and walk them through the plans and also provide them with plans of their areas so that they can move forward with planning the use of their allocated space.


𝗦𝘁𝗮𝗴𝗲 𝟮 𝗨𝗽𝗱𝗮𝘁𝗲:

Stage 2 is all the area south of the foreshore roadway including where the old surf club building is and all around the new Surf Club building lease area to the Caravan Park boundary and roadway.

• Engineering are close to completing the updated civil design works this had to be redone as the original building design for the Surf Club has been changed.

• The demarcation, levels and tie-in points with the Surf Club was finalised this week. 2/2/24.

• Sewer and irrigation pipe alignments will be finalised with the treatment plant project team by the end of next week. 11/2/24.

• It is anticipated receipt of For Tender drawings mid-Feb, with the aim to have the package out to market by the end of February 2024.

• Tenders will be open for 6 weeks and then go before Council for a final decision to proceed.


(Unfortunately, this is after the election, which until the results are known no certainty of any further stages can be guaranteed)


𝗦𝘁𝗮𝗴𝗲 𝟯 𝗨𝗽𝗱𝗮𝘁𝗲:

Plans on hold until after the election. If I am re-elected, I will fight to ensure all further stages of the Master Plan are delivered.


For further information and to view plans please follow the link below:






 
 
 